Tuesday, February 7, 2012

Drainage Update #13

Last week the work site was graded and 20 of the 23 pallets of sod needed were installed. Our goal this week is to finish the sod, apply pre-emerge and roll the entire area.

The second piece of the puzzle involves the homeowners lawn where the failed drainage pipe was removed. We have developed a punch list of items to be done over the next couple of weeks including sod,pinestraw and rock work to name a few.We have also been working closely with the owners to ensure they are satisfied with the end product.



Sod installation on 2/1