Thursday, February 16, 2012

#13 Project Update

The project that began in the middle of  December is nearly complete. Once the pipe was installed (mid Dec.) the weather worked against us in the way of frequent rains. Since the last week of January we have installed 24 pallets of sod and many landscaping plants. As of this morning there is a few detail items left to take care of.

This project would not have gone as smooth without the cooperation of the Lager's. Thank you for your patience and understanding.


Taken from the home owners lawn during the big dig



Same view but of the finished product



A portion of the finished area in the rough



Saturday, February 11, 2012

Greens

Due to the low temperture being at or below 22 degrees, greens will be covered this morning and remain covered until Mon. The tempertures that are used are at http://www.abc3340.com/. Below is a couple pics of #9 during the process.




 


Tuesday, February 7, 2012

Drainage Update #13

Last week the work site was graded and 20 of the 23 pallets of sod needed were installed. Our goal this week is to finish the sod, apply pre-emerge and roll the entire area.

The second piece of the puzzle involves the homeowners lawn where the failed drainage pipe was removed. We have developed a punch list of items to be done over the next couple of weeks including sod,pinestraw and rock work to name a few.We have also been working closely with the owners to ensure they are satisfied with the end product.



Sod installation on 2/1